Buffalo Main Street Project Update July 29 – Sheridan Media

The Wyoming Department of Transportation (WYDOT) has released the Buffalo Main Street Project update for the week of July 29.

Laura Dalles, senior public relations specialist with WYDOT District 3 in Sheridan,

said in the statement that the northern and southern bypass roads as well as the southern main street are paved and striped.

Crews will be paving the section of Rock Creek Road north of the I-90 interchange this week, so motorists are advised to expect delays, pilot cars and reduced speeds in that area.

The intersections of East and West Gatchell Streets will be closed from Monday, July 29 through Friday, August 2 so crews can pour the double gutters.

Finally, starting August 11, crews will begin working on North Main Street from the I-90 interchange to Hart Street.

We will post more weekly updates as they are released by WYDOT.